|
|
|
Home > Law > Law glossary > Law glossary
frustration of contract
Last modified: Thu Feb 23 16:37:37 2006
A contract is said to be `frustrated' if it becomes impossible to
perform, or if circumstances change to the extent that
performance would be substantially different from what was anticipated
by the parties. Consider the following (imaginary, but typical)
case. X offers 50,000 to Y to build an extension on
his (X's) house. X pays a deposit of 2,000, with an agreement
to pay the balance on completion. After
Y has started work, it becomes apparent that the ground around
X's house is not stable enough to support an extension, and
any attempt to do so would result in the foundations disappearing
rapidly into the ground. Y cannot, therefore, perform his part
of the contract. X has paid his deposit, but not got anything
in return. Y has incurred considerable expense in designing
the extension and getting in supplies. So X would like to
recover his deposit from Y, Y would like to recover his
expenses from X, and both parties would like to be released
from any further obligations under the contract.
The balance of losses in cases of frustration has been significantly
modified from the common law position by the
Law Reform (Frustrated Contracts) Act (1943). However, the
circumstances in which the courts are prepared to find
frustration have not changed, so the common law is
still relevant. In particular, in deciding whether frustration has
occurred, the courts have to balance two competing requirements.
On the one hand, there is the desire for certainty of contract.
Good business relations depend on an assumption that once a contract
has been entered into, it will be performed by both parties and,
if it is not, the wounded party is entitled to compensation.
The courts should not lightly intervene to set aside a good contract,
even if future events reveal it to be onerous for one party. It
would be difficult to do business at all if money received as part
of a contractual arrangement could not be spent until the contract
was fully performed, in case a court acted to undo the contract.
On the other hand there is the requirement to try to do justice
in the individual case. If it becomes impossible to perform
a contract owing to events beyond the control of the parties, it
is not particularly just that one party should end up having to
compensate the other when he is not at fault. This tension
is not easy to resolve, but in general the courts will not
set aside a contract that was good when it was made unless supervening
events have made it essentially impossible to perform, or
performance would render to one or other party none
of the benefit that was anticipated.
Although if a contract is frustrated it is deemed to be
discharged (see: DischargeOfContract), there remains
the problem of how any losses should be apportioned between the
parties. The rule at common law was first definitively
set out by the King's Bench
in ChandlerVWebster1904, although a number
of earlier cases had reached the same conclusion. This rule said
that the losses should `lie where they fall'. That is, any losses
incurred before the supervening frustrating event could not be
recovered. This was a simple rule, but a harsh one, and it was often
criticised. In our example of the extension builder, X would be
unable to reclaim his deposit and, indeed, would still be under
an obligation to pay the balance, this obligation having accrued
before frustration.
The finding of the House of Lords in TheFibrosa1943
partially overruled Chandler v Webster. In this case it was held
that, where there was a total failure of consideration, losses
that accrued up to the frustration would be recoverable. Under the
Fibrosa principle, X might be able to recover his deposit from Y,
as he has received none of the benefits that both parties expected
to be delivered by the contract.
The Fibrosa principle was given statutory backing in the Law Reform
(Frustrated Contracts) Act (1943). This says that monies paid under a
frustrated contract can be recovered, but the party that has receieved
payment is entitled to a quantum meruit award to
compensate him for expenditure he may have incurred in trying to
perform the contract. In the house extension case, the builders Y can be
forced to return the deposit they recevied from X, but they may be
entitled to be paid in respect of work they have already carried out.
ContractLaw
Law glossary index
|
|
|
|
Shameless plug
|
 By the author of this site. Buy on-line from Amazon USA | UK
|
|